DesignRiverbend Sports Complex

Riverbend Sports Field Improvements

Replacing field lighting on the four soccer fields and regrading two natural grass fields to fix drainage.

Project phase

  1. Planning (complete)
  2. Design (current phase)
  3. Procurement
  4. Construction
  5. Completed

Project overview

The 2003 field lighting at Riverbend has reached the end of its service life and spills light into the neighborhoods north of River Road. The project replaces it with directional LED fixtures that reduce spill and glare while cutting lighting energy use by an estimated 60 percent.

Fields 3 and 4 hold water after rain and are unplayable for days at a time each winter. Both will be regraded with new subsurface drainage and reseeded.

Scope of work

  • Replace field lighting on Fields 1 through 4 with directional LED fixtures
  • Install a lighting control system with scheduled shutoff
  • Regrade Fields 3 and 4 and install subsurface drainage
  • Reseed the regraded fields and establish turf over one growing season
  • Replace the spectator walkway between Fields 2 and 3 with an accessible paved route

Budget and funding

Funding sources for Riverbend Sports Field Improvements
Funding sourceAmount
Capital reserve$1,400,000
County regional park grant$700,000
Youth sports organization contribution$200,000
Total project budget$2,300,000

Project updates

  1. August 19, 2026

    Schematic design accepted

    The Board accepted schematic design at its August meeting. Photometric modeling shows light spill at the River Road property line falling below 0.1 footcandles, which meets the standard requested by neighbors at the April meeting.

  2. April 23, 2026

    Neighborhood meeting on lighting

    Twenty-eight residents attended the April 22 meeting. The main request was a firm shutoff time, which has been incorporated as an automatic 10:00 p.m. cutoff with no manual override.

Public involvement

How residents have been involved so far, and what is still to come.

  1. Neighborhood meeting on lighting and spill reduction, April 22, 2026
  2. Youth sports organization coordination meetings, quarterly
  3. Board review of 60 percent design documents, anticipated January 2027

Project documents