PlanningCedar Ridge Trail

Cedar Ridge Trail Extension

Extending the trail 2.8 miles north to connect with the county's Clearwater River path, including a new accessible trailhead.

Project phase

  1. Planning (current phase)
  2. Design
  3. Procurement
  4. Construction
  5. Completed

Project overview

The extension would link Cedar Ridge Trail to the county's Clearwater River path, creating a continuous 11-mile route and giving the Cedar Ridge and North Creek service areas a connection that does not require driving.

The project is in planning while the district completes environmental review and negotiates two easements. No construction schedule can be set until both are resolved.

Scope of work

  • Acquire two trail easements across private property
  • Complete environmental review and a biological resources assessment
  • Construct 2.8 miles of natural surface trail
  • Build a new trailhead with accessible parking, a restroom and a staging area
  • Construct a 60-foot span bridge over the north fork drainage
  • Install wayfinding signage along the full route

Budget and funding

Funding sources for Cedar Ridge Trail Extension
Funding sourceAmount
Open space acquisition fund$900,000
State recreational trails program, applied$600,000
Clearwater Trails Alliance contribution$150,000
Total project budget$1,650,000

Project updates

  1. September 1, 2026

    Trailhead location survey open

    A survey on the two remaining trailhead location options is open through October 30. Both options were presented at the May open house and the survey includes the tradeoffs identified for each.

  2. May 7, 2026

    Alignment open house held

    Forty-six residents attended the May 6 open house. The northern alignment drew stronger support, primarily because it avoids the steep section above Miller Creek.

Public involvement

How residents have been involved so far, and what is still to come.

  1. Board authorization to begin planning, January 13, 2026
  2. Open house on alignment options, May 6, 2026
  3. Community survey on trailhead location, open through October 30, 2026
  4. Environmental review public comment period, anticipated mid-2027

Project documents