CompletedOakview Park

Oakview Park Accessibility Upgrades

Rebuilt accessible routes from both parking areas, added accessible picnic tables and upgraded the restrooms.

Project phase

  1. Planning (complete)
  2. Design (complete)
  3. Procurement (complete)
  4. Construction (complete)
  5. Completed (current phase)

Project overview

This project addressed the highest-priority items identified for Oakview Park in the district's ADA transition plan. Routes from both parking areas were rebuilt to meet current slope and cross-slope standards, and accessible tables were added at both shelters.

The Board accepted the work as complete on April 14, 2026. Final cost came in at $511,300, about five percent under budget.

Scope of work

  • Rebuild accessible routes from the Oakview Avenue and Southgate Road lots
  • Restripe accessible parking stalls and add van-accessible spaces
  • Install five accessible picnic tables across both shelters
  • Replace restroom fixtures, hardware and signage
  • Add a ramped route and a ground-level activity panel at the playground

Budget and funding

Funding sources for Oakview Park Accessibility Upgrades
Funding sourceAmount
Capital reserve$340,000
Community development block grant$200,000
Total project budget$540,000

Project updates

  1. April 15, 2026

    Board accepts the project as complete

    The Board accepted a notice of completion on April 14. Final cost was $511,300 against a $540,000 budget, and the remaining funds returned to the capital reserve.

  2. March 30, 2026

    Work complete and park fully reopened

    All shelters, restrooms and the playground reopened March 27. Post-construction measurements confirmed every new route meets the running and cross slope requirements.

Public involvement

How residents were involved in shaping this project.

  1. Accessibility Advisory Committee review of the scope, August 2025
  2. Board award of construction contract, September 9, 2025
  3. Notice of completion accepted by the Board, April 14, 2026