
Oakview Park Accessibility Upgrades
Rebuilt accessible routes from both parking areas, added accessible picnic tables and upgraded the restrooms.
Project phase
- Planning (complete)
- Design (complete)
- Procurement (complete)
- Construction (complete)
- Completed (current phase)
Project overview
This project addressed the highest-priority items identified for Oakview Park in the district's ADA transition plan. Routes from both parking areas were rebuilt to meet current slope and cross-slope standards, and accessible tables were added at both shelters.
The Board accepted the work as complete on April 14, 2026. Final cost came in at $511,300, about five percent under budget.
Scope of work
- Rebuild accessible routes from the Oakview Avenue and Southgate Road lots
- Restripe accessible parking stalls and add van-accessible spaces
- Install five accessible picnic tables across both shelters
- Replace restroom fixtures, hardware and signage
- Add a ramped route and a ground-level activity panel at the playground
Budget and funding
| Funding source | Amount |
|---|---|
| Capital reserve | $340,000 |
| Community development block grant | $200,000 |
| Total project budget | $540,000 |
Project updates
Board accepts the project as complete
The Board accepted a notice of completion on April 14. Final cost was $511,300 against a $540,000 budget, and the remaining funds returned to the capital reserve.
Work complete and park fully reopened
All shelters, restrooms and the playground reopened March 27. Post-construction measurements confirmed every new route meets the running and cross slope requirements.
Public involvement
How residents were involved in shaping this project.
- Accessibility Advisory Committee review of the scope, August 2025
- Board award of construction contract, September 9, 2025
- Notice of completion accepted by the Board, April 14, 2026