Fairview Dog Park Shade and Water Improvements
Adding a second shade structure, replacing the water line and resurfacing the small-dog section.
Project phase
- Planning (current phase)
- Design
- Procurement
- Construction
- Completed
Project overview
Fairview Dog Park has one shade structure serving both enclosures, which leaves the small-dog section without shade through the afternoon. The water line running to the dog fountain has failed twice since 2024 and needs replacement rather than further repair.
The project is modest but frequently requested. It is programmed for construction in summer 2027 after the water line design is complete.
Scope of work
- Install a second shade structure over the small-dog enclosure
- Replace the water service line and both drinking fountains
- Resurface the small-dog section with new decomposed granite
- Add four benches and two waste station posts
Budget and funding
| Funding source | Amount |
|---|---|
| Capital reserve | $130,000 |
| Community donations | $50,000 |
| Total project budget | $180,000 |
Project updates
Project added to the draft capital plan
The project is included in the draft FY 2027 to 2031 Capital Improvement Plan, which the Board will consider at a public hearing on December 8, 2026.
Public involvement
How residents have been involved so far, and what is still to come.
- Public comment received at the June 9, 2026 board meeting
- Board programmed the project in the FY 2027 to 2031 CIP, pending December 8 adoption